Townsville Marine Project

Ports and Harbours,
Rivers and Waterways.

Principal:

Port of Townsville Limited

Location:

Benwell Road, Townsville

Ports and Harbouring Dredging Works at Townsville Marine Project

Overview of Project

Stage 1 of the Townsville Marine Precinct was an$88 million dollar extension of the Port of Townsville, designed to establish a world class facility for marine related industries.

This was a design and construct project completed as an alliance with the Port of Townsville Limited and Laing O’Rourke (LORAC).

Scope of Works

Neumann Dredging’s scope included the dredging of approx. 30,000m³ from the Ross River Channel to clear shoaling and using this material for initial land reclamation ,and the dredging of 410,000 m³ of hard and very hard clays of up to 400 Kpa from the new marina basin. The dredged material was pumped up to 700 metres and used for land reclamation purposes.

The operation was completed on a 24 hour, 6 day a week basis.

Innovations

Neumann Dredging had been working on an experimental Inline Lime Injection System (ILIS) that mixed Ag Lime to the dredged material whilst still in the dredge slurry pipeline. The ILIS was set up on the project for injecting the lime at a predetermined rate which then mixed with the PASS materials being dredged.

After some initial trials, the ILIS proved to be successful in injecting the predetermined amount of lime at the required dosing rate into the dredge pipeline for neutralisation of PASS materials that were dredged from the Marina basin.

Challenges

  • Dredging stiff, very stiff and hard clays
  • Coordinating dredging activities with other contractors
  • Working in partially open waters during most of the project
  • Completing the dredging program on time whilst removing difficult materials